Consolidated timeline across all active project schedules, broken out by phase. Use Focus on phase, the Phase comparison table, or open a single project's full Design Schedule. Section headers collapse.
Each project's bar is broken into phases. Pick a phase below to spotlight it across every project (the rest dims and each bar shows that phase's dates and duration).
Rithy's request: Procurement, Fabrication, FAT, and Commissioning/SAT broken out for every project. Durations are working days (wd) from the source schedule where stated. Cells marked pending or — are awaiting the PM team's standardized callouts.
| Project | Procurement | Fabrication | FAT | Commissioning / SAT |
|---|
| Project | Client | Stage (Jun '26) | NTP / Start | Design Complete | Mech. Completion | Final Completion | Source |
|---|