Master Project Schedule

Consolidated timeline across all active project schedules, broken out by phase. Use Focus on phase, the Phase comparison table, or open a single project's full Design Schedule. Section headers collapse.

Prepared by Alexander Asante Data as of June 18, 2026 Source: All Active Project Schedules
15
Active projects tracked (TCC = 1)
21
Schedules read (incl. TCC sites)
Mar '24 – Apr '28
Portfolio window
Aug 31, 2026
Next final completion (Burnt Peak)

Portfolio Timeline

Each project's bar is broken into phases. Pick a phase below to spotlight it across every project (the rest dims and each bar shows that phase's dates and duration).

Focus on phase
Filter by client
Design
Procurement
Fabrication
FAT
Construction
Commissioning / SAT
Milestone
Final completion

Phase Comparison — Start · End · Duration

Rithy's request: Procurement, Fabrication, FAT, and Commissioning/SAT broken out for every project. Durations are working days (wd) from the source schedule where stated. Cells marked pending or are awaiting the PM team's standardized callouts.

ProjectProcurementFabricationFATCommissioning / SAT

Milestone Detail

ProjectClientStage (Jun '26)NTP / StartDesign CompleteMech. CompletionFinal CompletionSource

Design Schedule

Select project

Design
Procurement
Fabrication
FAT
Construction
Comm / SAT
Completed ✓
In progress
Upcoming
Milestone
Status & open items (for the PM team / Rithy).
  • TCC is broken out into its 7 village sites (Ft Yukon, Grayling, Huslia, Minto, Ruby, Tok, Venetie) — each its own schedule. Timelines split: Minto & Tok complete Nov ’26 (road / Tacoma access), while the barge/air villages run to mid-2027 (fabrication parks on a schedule hold until spring ’27). Also added earlier: Kantishna (two-season build) and NVE Mt. Charleston (RFP engineering schedule).
  • CATAPULT (CEC) stays a single row — it's one schedule file covering its 7 Mini Box sites (install program, Jul–Sep ’26), unlike TCC's separate per-site files. Rule going forward: a project with multiple schedule files gets broken out; a single multi-site file stays one row.
  • Fabrication / FAT / SAT are populated wherever the source breaks them out; SAT vs "Commissioning" is reconciled under one column. Still pending PM breakout: HUC-CPRG and RG 773 commissioning, and HUC Turquoise fabrication (one date).
  • Pyramid Lake and Burnt Peak track Procurement/Fab/FAT in earlier factory schedules. NVE Mt. Charleston is engineering-stage, so build phases aren't scheduled yet.